Construction Cost Calculator

To calculate construction costs, choose a construction group and construction code.
Heated Sq Ft
Construction Group
Construction Code
Non-Heated Sq Ft
Construction Group
Construction Code

  1. Private Garages use Utility, miscellaneous
  2. For shell only buildings deduct 20 percent
  3. N.P. = not permitted
  4. Unfinished basements (Group R-3) = $21.00 per sq. ft.

GroupIAIBIIAIIBIIIAIIIBIVVAVB
A-1 Assembly, theaters, with stage 341.86 330.34 322.57 310.34 291.96 282.93 300.86 270.73 262.11
A-1 Assembly, theaters, without stage 312.84 301.33 293.56 281.32 262.95 253.92 271.85 241.72 233.10
A-2 Assembly, nightclubs 275.09 266.93 259.34 250.54 234.96 228.26 241.54 213.57 206.65
A-2 Assembly, restaurants, bars, banquet halls 274.09 265.93 257.34 249.54 232.96 227.26 240.54 211.57 205.65
A-3 Assembly, churches 317.43 305.92 298.14 285.91 267.99 258.96 276.44 246.76 238.14
A-3 Assembly, general, community halls, libraries, museums 270.80 259.29 250.52 239.28 220.19 212.16 229.81 198.96 191.35
A-4 Assembly, arenas 311.84 300.33 291.56 280.32 260.95 252.92 270.85 239.72 232.10
B Business 265.63 255.90 246.45 236.05 215.01 206.57 226.78 189.75 181.18
E Educational 282.69 273.02 265.84 254.38 237.44 225.45 245.61 207.53 201.06
F-1 Factory and industrial, moderate hazard 161.70 154.21 144.70 139.94 124.72 118.51 133.72 103.40 96.83
F-2 Factory and industrial, low hazard 160.70 153.21 144.70 138.94 124.72 117.51 132.72 103.40 95.83
H-1 High Hazard, explosives 150.85 143.36 134.84 129.08 115.17 107.96 122.87 93.86 N.P.
H234 High Hazard 150.85 143.36 134.84 129.08 115.17 107.96 122.87 93.86 86.28
H-5 HPM 265.63 255.90 246.45 236.05 215.01 206.57 226.78 189.75 181.18
I-1 Institutional, supervised environment 269.11 259.88 252.15 241.97 222.52 216.37 242.28 199.48 193.49
I-2 Institutional, hospitals 442.38 432.64 423.19 412.79 390.61 N.P. 403.53 365.36 N.P.
I-2 Institutional, nursing homes 307.72 297.98 288.54 278.13 258.63 N.P. 268.87 233.38 N.P.
I-3 Institutional, restrained 301.48 291.74 282.29 271.89 252.65 243.22 262.63 227.40 216.82
I-4 Institutional, day care facilities 269.11 259.88 252.15 241.97 222.52 216.37 242.28 199.48 193.49
M Mercantile 205.22 197.06 188.47 180.67 164.83 159.13 171.67 143.44 137.53
R-1 Residential, hotels 271.95 262.72 254.98 244.80 225.03 218.88 245.11 201.99 196.00
R-2 Residential, multiple family 227.64 218.41 210.68 200.50 182.02 175.88 200.81 158.99 153.00
R-3 Residential, one- and two-family 212.00 206.26 200.94 195.99 190.28 183.39 192.66 176.52 166.08
R-4 Residential, care/assisted living facilities 269.11 259.88 252.15 241.97 222.52 216.37 242.28 199.48 193.49
S-1 Storage, moderate hazard 149.85 142.36 132.84 128.08 113.17 106.96 121.87 91.86 85.28
S-2 Storage, low hazard 148.85 141.36 132.84 127.08 113.17 105.96 120.87 91.86 84.28
U Utility, miscellaneous 115.48 108.95 102.64 98.13 88.49 81.89 93.86 69.76 66.48